# GP → ZPA migration plan — prereq, implement, rollback

Source: https://ai.techclick.in/blog_paloalto_globalprotect_to_zpa_migration_plan
Markdown: https://ai.techclick.in/blog_paloalto_globalprotect_to_zpa_migration_plan.md
Publisher: Techclick Infosec Pvt Ltd

Migration-only lesson: GlobalProtect to ZPA prerequisites, implement plan, data scenarios, and a written rollback. Training sample: Apex Freight 200 users.

## The Friday cutover ticket

 Ticket: “Turn off GlobalProtect this weekend. ZPA is installed.” That is not a migration. A migration has a data pack, a wave list, pass/fail numbers, and a rollback owner. Zscaler’s own VPN-to-Zero-Trust sequence is assess → map apps → least-privilege policy → deploy → IAM → test. You do not skip to “disable the portal.”

   Hero · plan before cutover

   Cutover is a wave, not a company-wide switch. The old GlobalProtect portal stays committed until the last wave has proof.

   Quick answer

   Do not migrate “the VPN.” Migrate named applications to named groups. For Apex Freight (training sample): 200 GP users, 2 DCs, 12 publishable apps. Week 0 freeze GP. Week 1 IdP+SCIM+connectors. Week 2 ERP/jump/WMS as defined segments plus a discovery wildcard. Week 3 dual-run 20 Finance users. Week 4 next wave only if P1–P7 pass. Rollback unit = one IdP group. Discovery dies last.

## Apex Freight data pack (training sample)

 All numbers below are a classroom scenario, not a live customer. Use them as the sheet you would actually build from GlobalProtect logs, firewall rules, and the IdP.

   Inventory · apps into groups into policy

   If a row has no owner group and no ports, it is not ready to become an Application Segment.

        Fact  Training value  Why it matters

        Company  Apex Freight (sample)  Two DCs: Mumbai HQ apps, Pune warehouse apps
        GP users  200 always-on clients  Never move all 200 on day one
        IdP groups  Finance 35 · Ops 80 · HQ 70 · Contractor 15  SCIM must show these counts before policy
        Sites  Mumbai DC + Pune DC  One connector group per site, same geo inside a group
        GP objects to keep  Portal  gp.apexfreight.example  + gateways  gp-mum ,  gp-pun   Rollback path. RFC-style names only
        Discovery (temporary)   *.apexfreight.internal  + authenticated-employee Allow  Safety net. Not the end state

### Application inventory extract (do not publish the last two rows)

        App  FQDN / target  TCP/UDP  Site  Owner group  Class

        ERP   erp.apexfreight.internal   80, 443, 8443  Mumbai  Finance  Crown jewel — define week 2
        Finance files   finfiles.apexfreight.internal   445  Mumbai  Finance  Crown jewel
        Jump host   jump-mum.apexfreight.internal   3389 TCP+UDP  Mumbai  Ops  Crown jewel — ICMP from connectors
        AD / DFS   dc01.apexfreight.internal   88, 135, 389, 445, 636  Mumbai  HQ  Crown jewel — local connector group
        WMS   wms.apexfreight.internal   443  Pune  Ops  Define before Pune wave
        Vendor portal   vendors.apexfreight.internal   443  Pune  Contractor  Tight Allow + Block anything else
        Intranet   intranet.apexfreight.internal   443  Mumbai  HQ  Known app — week 4
        HR   hr.apexfreight.internal   443  Mumbai  HQ  Known app
        Printer VLAN   10.40.12.0/24   any  Pune  —   Do not publish  — not an application
        Camera VLAN   10.40.20.0/24   any  Pune  —   Do not publish  — old VPN habit

   Data rule

   If the inventory row is a subnet with no owner, it is not a ZPA application. Publishing  10.40.12.0/24  rebuilds GlobalProtect inside ZPA.

## Prerequisites (gate, not a wish list)

 Week 1 does not start until every row is green. A red row is a stop, not a “we will fix it in the pilot.”

        Gate  Apex Freight pass  Fail = stop

        ZPA license / tenant  ZPA edition that includes App Connectors is live  No connectors, no path
        SAML IdP  Entra (or Okta/Ping) app for ZPA; same NameID style as GP  Users cannot authenticate
        SCIM first cycle  Finance 35, Ops 80, HQ 70, Contractor 15 visible in ZPA  Do not write group policy yet. Source: Access Policy deployment guide
        Connector hosts  2× Mumbai + 2× Pune. Min 4 GB / 2 CPU; Zscaler recommends 8 GB RAM. Plan ~500 Mbps each, N+1  Single VM = no rollback inside the site
        Connector network  Outbound TLS 443 to ZPA. Internal DNS. App ports. ICMP to servers (mandatory for UDP)  User sees “app down”
        No ZIA hairpin  Connector outbound does  not  go via ZIA PSE  Zscaler does not recommend this
        ZCC + bypass  App Profile lists  gp.apexfreight.example ,  gp-mum ,  gp-pun  in  VPN Gateway Bypass   Dual-run flaps
        GP stay-alive  Portal + both gateways still committed, licensed, certs &gt; 60 days  No parachute

## Implement plan (4 weeks)

   Journey · prereq → dual-run → wave → rollback ready

   Rollback is a column on the plan, not an appendix you write after the outage.

   Flow 1 · Apex Freight weeks

       Four week migration: freeze, build, dual-run, wave

- Week 0–1 Freeze GP · IdP · SCIM Week 2 4 connectors · ERP/WMS Week 3 20 Finance dual-run Week 4+ Ops / Pune / contractors GP portal stays live through every box. Discovery wildcard dies after week 8–12, not week 3. Each arrow is a gate. If SCIM counts are wrong, you do not install ZCC on Finance laptops. #### Week 0 — Freeze GlobalProtect Export portal/gateway config. Snapshot HIP and split-tunnel. No “clean up unused gateways” this week. Source: GlobalProtect Overview .

- #### Week 1 — Identity Stand SAML. Run SCIM. Do not write Access Policy on groups until the first cycle shows 35/80/70/15. Source: Access Policy deployment guide .

- #### Week 2 — Connectors + first segments Groups DC-Mumbai and DC-Pune , N+1 each. Define ERP, finfiles, jump, WMS. Add discovery *.apexfreight.internal under them. Crown jewels get Allow + Block Any. Source: ZPA Leading Practices .

- #### Week 3 — Dual-run wave 1 IdP group zpa-wave-finance = 20 of 35 Finance. ZCC via Intune. VPN Gateway Bypass complete. GP still on the laptop. Run P1–P7 for five business days.

- #### Week 4+ — Expand only on numbers Wave 2 = 40 Ops (Mumbai jump + later Pune WMS). Wave 3 = contractors on vendor portal only. After 60–90 days or ~60% entitled users, turn discovery off. Source: same leading-practices guide.

## Do — Side A / B / C

### Side A — IdP and GP stay-alive

- #### Confirm SCIM counts match the data pack If Finance shows 12 not 35, stop. Policy will deny the missing 23 and they will look like a ZPA outage.

- #### Create wave groups in the IdP zpa-wave-finance , zpa-wave-ops , zpa-wave-contractor . These are the rollback units. Nested under the department groups.

### Side B — ZPA objects for Apex Freight

     https://admin.zscaler.com · Policies → Access Control → Private Applications → Defined Application Segments

     Training mock · not live

       Policies → Access Control → Private Applications → Defined Application Segments → Add

### Add Application Segment

          Name  ERP-Production

          TCP ports  80, 443, 8443

        Applications  erp.apexfreight.internal

          Connector group  DC-Mumbai

          Server group  Dynamic discovery

        Cancel  Save

   Copy every port from the inventory (8443 included). Path: Configuring Defined Application Segments. Sample FQDN only.

  Access Policy order for Apex Freight (first-match)  1 Allow  ERP-Production              memberOf = Finance
2 Block  ERP-Production              Any
3 Allow  WMS-Production              memberOf = Ops
4 Allow  Vendor-Portal               memberOf = Contractor
5 Block  Vendor-Portal               Any
6 Allow  *.apexfreight.internal      authenticated employees   ← discovery
7 Block  Any                         memberOf = Contractor     ← contractors stay in their box
8 Block  Any                         Any                       ← enable only after discovery ends

 Source:  Configuring Access Policies . Most-specific segment wins; missing ports do  not  fall back to row 6.  Understanding Application Access .

### Side C — Dual-run

 ZCC App Profile: VPN Gateway Bypass = portal + both gateways. Do not use forwarding-profile Tunnel on a VPN-trusted network. Assign ZCC only to the current wave group. Source:  Configuring ZCC App Profiles .

## Five data scenarios

 Use these in class or in a design review. Numbers are from the Apex Freight pack.

### S1 — Greenfield wave 1 (Finance)

  Given:  200 on GP, ZPA built, discovery on, ERP defined with 80/443/8443.  When:  20 Finance laptops get ZCC.  Then:  P2 =  https://erp.apexfreight.internal  shows policy  Allow ERP-Production  and connector  DC-Mumbai . A contractor who types the same URL hits rule 2 Block. GP still works for the other 180.

### S2 — Discovery leftover (the recruiter hire)

  Given:  Someone left  *.apexfreight.internal  as the only segment for 90 days.  When:  you are hired to “create the rest of the app segments.”  Then:  export discovery, carve ERP/WMS/vendor first, put group Allows  above  discovery, copy every live port, do  not  delete the wildcard this week. Full script:  recruiter ticket on the concept lesson .

### S3 — Missing port after carve-out

  Given:  You created  ERP-Production  with only TCP 443. Users also open 8443 (from the inventory).  When:  Finance hits 8443.  Then:  more-specific segment wins; 8443 is not listed; session  drops . It does not use discovery. Fix = add 8443 to the defined segment, not “open the wildcard again.”

### S4 — Pune site down

  Given:  Both  DC-Pune  connectors Offline (outbound 443 blocked after a firewall change). Mumbai healthy.  When:  Ops cannot open WMS. ERP still works.  Then:  rollback unit is  zpa-wave-ops  only if they have no GP fallback — or leave them on GP for Pune apps. Do  not  disable ZPA company-wide. Restore connector egress, then re-test WMS from a Pune connector:  dig  +  curl .

### S5 — Contractor lateral-move attempt

  Given:  Contractor is in SCIM group Contractor. Discovery Allow exists for employees. Rule 7 Blocks Any for Contractor.  When:  contractor tries  erp.apexfreight.internal  and  dc01 .  Then:  Vendor-Portal Allow may hit for the vendor URL; ERP and AD must hit Block. If they succeed, your discovery Allow is above the contractor Block — reorder tonight.

        Scenario  First evidence field  Wrong first move

        S1 Finance pilot  Diagnostics: user, ERP-Production, DC-Mumbai, rule 1  Disable GP for all 200
        S2 Discovery leftover  Discovered FQDN list + who touched it  Delete wildcard Friday
        S3 Missing 8443  Segment ports vs client dest port  Rebuild SAML
        S4 Pune down  Connector group health, only WMS failing  Company-wide rollback
        S5 Contractor  Policy name on the deny  Publish printer VLAN so they “just work”

## Rollback plan

   Ops · rollback is a scored decision

   Write the trigger numbers before wave 1. “It feels bad” is not a trigger.

   Flow 2 · rollback unit

       Rollback by blast radius: one user, one wave, or one site

- Trigger 1 user / 1 app → fix segment 1 wave → drop ZCC group 1 site / IdP down → that site GP portal + gp-mum + gp-pun still live ZPA connectors and policies stay standing Apex Freight never rolls back “the company.” It rolls back a wave group or a site’s apps. Trigger (write this in the CAB) Action Leave standing >10% of the current wave fail a P1 app for 30 minutes Remove that wave from ZCC assignment. GP reconnects All segments, all connectors Connector group for one site N+1 gone Park only apps in that site; keep other site on ZPA Other site’s group IdP outage Users with valid ZPA session may ride timeout (default 7 days). New auth fails — use GP Do not delete the IdP app P7 drill failed on a real user Do not start the next wave Current wave stays or rolls back #### Declare the trigger in the ticket Example: “WMS P1 fail 14/40 Ops for 35 minutes. S4. Rolling back zpa-wave-ops.”

- #### Stop the bleed Pull the wave group from ZCC. Optional: Access Policy Block for that group so half-connected laptops do not black-hole FQDNs.

- #### Prove GP Same users open ERP/WMS over GlobalProtect. HIP and old security rules still match.

- #### Fix ZPA, then re-enter the wave through P1–P7 Do not invent a new weekend cutover.

- #### Retire GP last When every in-scope group has been on ZPA past the discovery deadline and P7 unused for 30 days: remove gateway DNS, then portal, then licenses — that order only.

## Proof and traps

   Wave exit (Apex Freight)

- P1–P5 pass for ≥95% of the wave (19/20 Finance).

- P7 rollback drill: one named user, ticket number, time-to-GP recorded.

- Diagnostics show segment name + policy name, not only “connected.”

- Connector group still N+1 after the wave’s traffic.

- No new /24 “just this once” published.

        Trap  Apex Freight example  Fix

        Migrating the network  Publishing printer + camera VLANs  Delete those segments. Apps only
        SCIM used too early  Finance policy while SCIM shows 12  Wait for 35, then wave
        More-specific drop  ERP segment missing 8443  Add the port. Do not delete the segment
        Dual-run fight  Bypass missing  gp-pun   Add every gateway FQDN/IP
        Discovery forever  Wildcard still there after month 6  Calendar kill + request path for new apps

   Say this in CAB

   “We are not replacing a VPN concentrator this weekend. Apex Freight moves 20 Finance users to named segments with GP still live. Rollback is remove zpa-wave-finance. Discovery stays until the long tail has owners.”

## Knowledge check

   Six items on the Apex Freight data. Check answers when done.

       Q1
       SCIM shows Finance = 12. The data pack says 35. Wave 1 is scheduled tomorrow. What do you do?

           Install ZCC anyway — SAML login is enough
           Stop. Fix SCIM until 35 land, then write group policy and start the 20-user wave
           Publish 10.0.0.0/8 so the missing 23 still reach ERP
           Disable GlobalProtect so the 12 users are forced onto ZPA

       Correct:  b . Re-read Prerequisites. Group policy on incomplete SCIM looks like a random outage.

       Q2
       Apex Freight has 200 GP users. What is the correct first implement wave?

           20 Finance users, dual-run, GP still installed
           All 200 on Saturday so helpdesk has one ticket pile
           Contractors first because they complain the most
           Pune warehouse first because WMS is “easy HTTP”

       Correct:  a . Re-read Implement plan. Crown-jewel Finance + small ring. Pune is a second site and a second connector group.

       Q3
       Inventory has  10.40.12.0/24  printers and  erp.apexfreight.internal  80/443/8443. What becomes Application Segments?

           Both — users need printers through ZPA
           Only the /24, because ERP can stay on discovery
           Neither until GlobalProtect is deleted
           ERP (and other named apps). Never the printer VLAN

       Correct:  d . Re-read the data pack. A subnet with no owner is not an application.

       Q4
       You carved ERP-Production with TCP 443 only. Users still open 8443. What does ZPA do?

           Fall back to  *.apexfreight.internal  discovery
           Match the more specific ERP segment and drop 8443
           Send the user to GlobalProtect automatically
           Open all ports on DC-Mumbai

       Correct:  b . Re-read S3 and Understanding Application Access. Copy every inventory port onto the defined segment.

       Q5
       Both DC-Pune connectors go Offline. Mumbai is healthy. Who do you roll back?

           The entire company, including Finance ERP
           Delete all Application Segments
           Only the Pune-dependent wave/apps (WMS / vendor). Leave Mumbai ZPA up
           Decommission the GlobalProtect portal so users stop mixing paths

       Correct:  c . Re-read S4 and Rollback. Blast radius = site or wave, never “burn GP.”

       Q6
       Week 12: 90% of entitled users hit defined segments. Discovery is still Allow Any employee. Next move?

           Leave discovery forever — it is safer
           Disable the wildcard on the calendar date, keep a request path for new apps, then consider fail-closed
           Replace discovery with 10.0.0.0/8
           Turn GlobalProtect back on for everyone

       Correct:  b . Re-read Implement week 4+ and S2. Discovery without a deadline is a cloud VPN.

       Check answers
       Reset

## Sources

- Zscaler — Migrate from VPN to the Zero Trust Exchange

- Zscaler — ZPA Leading Practices (discovery window, N+1, 500 Mbps, geo groups)

- Configuring Defined Application Segments

- Understanding Application Access

- Configuring Access Policies

- App Connector Deployment Prerequisites

- ZCC App Profiles / VPN Gateway Bypass

- Palo Alto — GlobalProtect Overview

 Related:  Concept + Rahul + recruiter ticket  ·  App Connectors  ·  ZPA access policy  ·  GlobalProtect lesson

---